Lead time

Injection Molding Lead Time: What Sets the Clock

Lead time means different things on different lines of a program plan. Mixing them is how schedules slip quietly.

Two clocks

Tooling lead time is not production lead time

Injection molding lead time searches blend tool build, sampling, material lead, and shipping. Only the tooling portion has an approved public figure.

NetProto publishes tool build duration in business days with a qualifier. Production scheduling after the tool is released varies by program and is quoted per order, not as a site wide number.

Definitions

Which clock you are measuring

ClockStartsStopsPublic figure on NetProto
Tool buildOrder and DFM acceptanceHardened steel tool complete10 business days on qualified programs
T1 samplingTool completeCustomer approval criteria metProgram specific
Production orderReleased tool and POParts shipNot published; use quote
ReorderPO on existing toolParts shipNot published; use quote

Calendar math

Straight to steel versus staged tooling on the calendar

Count every gate, not just the first cut date.

One steel tool path

  • One DFM cycle before steel.
  • One tool build window.
  • One sampling cycle on production steel.

Staged tooling path

  • First tool build and sampling.
  • Design freeze assumed before second tool.
  • Second tool build and second sampling.

Schedule checklist

Inputs that shorten or lengthen the tool clock

  • CAD completeness when DFM starts.

  • Resin family chosen or narrowed.

  • Cosmetic and texture decisions settled.

  • Customer review turnaround on DFM and samples.

Track the program

See status after the quote

Online tracking reduces email chasing during the approved tool build window.

  • Instant quote and DFM entry point
  • Project tracking for qualified programs
  • Same tool used when production starts
Project timeline sketch for tooling and first production

Related timing pages

FAQ

Lead time questions

Can you ship production parts in two weeks?

We do not publish production lead times. After the tool is released, request a production quote for schedule.

Does tool build time include shipping the mold to me?

The approved figure covers completed steel tool build. Mold export logistics are separate; see export molds.